Construction Ahead

Construction Projects

Cascade Natural Gas Corporation is in the process of replacing and updating service lines within our service territory. This is an ongoing program to ensure our customers safe and efficient natural gas service now and well into the future.

As a result of this construction, you may see some disruption of your normal traffic routes during the day. This construction activity will be kept as minimal as possible and will be cleaned up daily. Customers within the area of the replacement will be contacted regarding updating their lines and meters as the construction crew draws near. See below for more details about construction in your area. 

Bend, Oregon

Cascade Natural Gas Corporation Phase 3 pipe replacement:

Latest Update: November 14, 2014

Crews have one service left to replace on NW 5th Street and six services to replace or tie over in the alley between NW Portland Avenue and NW Roanoke Avenue. The tie in of the two-inch main on NW Portland Ave and NW 5th Street will be completed on Monday. Crews will then move back into the alley between NW Ogden Avenue and NW Portland to continue on the installation of the main expecting to reach the tie in point by Friday, November 21st. 

There will be minimal impact on traffic from the work remaining to complete on NW Galveston Avenue where crews bored under the Deschutes River.

 

Bend Construction Work
Figure 1. - Construction work continues in Bend, OR.
 

Latest Update: November 7, 2014
Crews continue to reconnect service lines to the new main on NW 5th St. and a paving crewing is following behind working on restoration. There will continue to be traffic control in this area until the middle of next week.

Work also continues in the alley between NW Portland Avenue and NW Ogden Avenue. They are working westward and are expected to reach NW 7th Street by Monday, continuing on toward NW 9th Street.

The bore crew has completed the task of pulling the six-inch steel line under the Deschutes River. Crews are still in the area performing clean-up and removing equipment. Starting Monday, November 10th, the team will begin the testing of this line. This work is not expected to impact traffic in the area.
  

Additional Information

Updates will be posted here and on Cascade's Facebook page.

See the outlined areas on the map below for more detail on the streets affected. Click on the map for a closer view. For more information, please contact us by email at BendReplacementProject@cngc.com, or by phone at (888) 522-1130, or speak with our field personnel on site at any time. We are committed to our community and your input is very important to us. All inquiries are welcome and will be answered promptly.


Longview, Washington - New West Side

Latest Update: September 12, 2014

Longview, Washington, New West Side
: Construction on Phase lll of the pipeline replacement project is under way and is expected to be completed in mid-October. The project is approximately 50 percent complete with installing new mains and services, including converting customers’ fuel lines.

See the outlined areas on the map below for more detail on the streets affected. Click on the map for a closer view. For more information, please contact us by email at Newwestside@cngc.com, or by phone at (360) 577-4812, or speak with our field personnel on site at any time. We are committed to our community and your input is very important to us. All inquires are welcome and will be answered promptly.